Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

Notices

PUBLIC NOTICE 1: ELECTRICAL TARIFFS (AMP LIMIT) – Phase 2 of Power Limit Adjustment Project

The George Municipality embarked on process to phase in a new electricity tariff structure. This process started on 1 July last year, and is in line with the National Energy Regulator of South Africa (NERSA) approved cost of supply study for George as well as the municipal Electricity Pricing Policy. The municipality has been effecting these changes in a variety of ways so as to limit the impact on our consumers as far as possible.

PHASE ONE ROLLOUT – has included to date:

  • Consumers were provided with an opportunity to select their Amperage capacity, in line with their household power requirement.
  • Consumers who had not yet made a selection for their capacity (AMPS) by 1 July 2022, were then placed on a capacity selected by the municipality. The capacity selection is based on the consumers historic consumption (12 months prior). The option remains open for these consumers to make a change and select their own capacity.
  • George Municipality has sent out field teams to visit residents at home and implement the changes, where for example a resident has applied and chosen a capacity for their house; and/or where no selection was made and the municipality then applied a capacity based on historic consumption.
  • Consumers were also given the opportunity to make a capacity selection while a field team was at their home – so doing to minimise the impact of a Consumer making a choice which then does not work for them and having to get the field team in back to make a change again.
  • Communication through various platforms continued to request consumers to make their selection timeously.

Thousands of Consumers have had the Capacity (AMPS) addressed through either their own selection OR by the municipal capacity selection. George Municipality has already successfully implemented power limit adjustments on thousands of it’s prepaid meter base, through the work done by field staff following the applications received from consumers for a specific capacity or by the municipality making the decision for Phase 1 power limit based on historic consumption. The field teams will continue to go out weekly to do Amperage limit roll-out and site inspections on prepaid meters.

IMPORTANT TO NOTE: Consumers who have already made their selection will NOT be affected by Phase 2 of the Power Limit Adjustment Project.

What about Consumers who have not yet made a selection?
The consumers who have not made a selection yet or who are not happy with the selection made by the municipality based on historical consumption, are encouraged to do so speedily on the details shared below. The first and most preferred option is always for our consumer to select the capacity their require. Consumers are allowed one opportunity per financial year to make such a change in capacity.

PHASE TWO ROLLOUT – POWER LIMIT ADJUSTMENT PROJECT will take place as follows:
From the 1st April 2023, the municipality will Apply the following Capacity Selection based on the historic consumption:

  •  If consumer had a 12 month average historic monthly consumption of above 400 units (kWh) and below 600 units (kWh), the consumer will be placed on a 30A;
  •  If consumer had a 12 month average historic monthly consumption of above 600 units (kWh) the consumer will be placed on a 40A;
  • Indigents consumer will not be impacted by this phase, as all indigent consumers are dealt with in line with the Indigent Policy.
  • All consumer who have already made their selections will not be impacted.

    Key Reminders on the applicable Electrical Tariffs are:
  • Small Domestic and Commercial tariffs (that is Prepaid and conventionally metered Consumers) are linked to the capacity limit of supply they choose.
  • Consumers who are willing to manage their loads within a capacity limited to 20 Amps Single Phase are offered a subsidised tariff with no fixed charges.
  • All Consumers who require more than 20 Amp capacity are charged a phased-in Cost Reflective Tariff with:
    – a Fixed Basic Charge,
    – a Capacity Charge depending on the capacity limit of the supply and
    – a lower Energy Charge.
  • Bulk consumers have all been moved to a Time of Use tariff.
  • Small Scale Energy Generators (SSEG) consumers are subject to fixed and Time of Use energy charges. Further information on understanding the potential electricity cost and management of loads, and how to make a decision about the capacity you can choose will be provided.Bear this in mind when making your choice:
  • Capacity selection by the municipality based on the consumers historic consumption was for a financial break-even to reduce the impact on the customer and not necessarily to confirm the capacity required.
  • The Municipality cannot determine the optimal capacity required with the available meter data, therefore consumers must determine what their energy and capacity requirements are.
  • The municipality has noted that customers are selecting the capacity as low as possible to reduce cost without understanding the implications. This is evident by the number of upgrades required once a selection is implemented. Please consider your selection carefully.Do you want to discuss your energy consumption and find out what the best Capacity will be for your needs, phone 044 801 9243, have your Municipal Account Number and Prepaid Meter Number handy OR email your query to elec.applications@george.gov.za

Link to Application Form to Select Capacity
Link to Bulk Demand Application Form
Link to Excel Calculator – establish how many units you will receive for cash value and do the comparisons with selection of either 30/40/50 or 60 Amps
https://www.george.gov.za/wp-content/uploads/2022/06/Elec-Tariff-Easy-Customer-test.xlsx

Note: The excel spreadsheet must be downloaded from the link and enabled for editing. It will not work on cellphones that do not have Excel Viewer (XLXS Reader)

Eskom Load shedding update – 10 March 2023

*#Eskom Load shedding update – Stage 4 will be reduced to Stage 3 over the weekend with Stage 1 loadshedding possible for Sunday morning.*

_*Issued by George Municipality on behalf of Eskom – 10 March 2023*_

(See changes to Uniondale schedule added)

 

*George will be affected as follows:*

Friday 10/03/2023

18:00 – 20:30

Saturday 11/03/2023

02:00 – 04:20

18:00 – 20:30

Sunday 12/03/2023

02:00 – 04:30

10:00 – 12:30

Monday 13/03/2023

00:00 – 02:30

08:00 – 10:30

16:00 – 18:30

 

*Please note that the Uniondale network has just been normalised by Eskom. The Uniondale original schedule will therefore be active again _*AND WILL NOT RUN ON THE MISGUND SCHEDULE*_

*Uniondale will be affected as follows:*

Friday 10/03/2023

21:00 – 23:30

Saturday 11/03/2023

05:00 – 07:20

21:00 – 23:30

Sunday 12/03/2023

13:00 – 15:30

Monday 13/03/2023

03:00 – 05:30

11:00 – 13:30

19:00 – 21:30

 

SWITCHING ON AFTER LOADSHEDDING – Not all areas will be switched back on at the same time!

Residents of George must please note that with the extended load-shedding, our Electrotechnical Directorate is no longer able to switch the entire city back on at the same time. Our daily notifiable demand from ESKOM has historically been set at 85MVA and on average George would use between 60 and 80MVA, although the municipality must pay ESKOM for 85MVA.

If the power is returned simultaneously to all areas when load-shedding ends, this creates a massive spike or surge in power with all geysers, freezers/fridges/batteries, etc., drawing power simultaneously. With the extended four-hour load-shedding, the spikes for George are consistently reaching 105 – 112 MVA.

Areas will be switched on in sections, on rotation after Load-shedding.

Eskom has indicated that unless George can reduce the spikes, they will increase our notifiable demand to the highest actual usage level which will in turn increase the purchase cost to the municipality. Consumers are requested to use electricity very sparingly when power returns after load-shedding (especially a 4-hour slot).

The municipality will now in rotation, switch the power on in sections. This means if for example the load-shedding slot is scheduled from 20h00 – 22h30, there is a chance that your area may only come on at 22h45 or 23h00.

Please do not switch high-usage equipment on immediately after Load-shedding.

Consumers are therefore urged to turn off high-usage equipment and where possible to not switch on appliances such as stoves and kettles for at least 30 minutes after load shedding. This will reduce the risk of overload tripping on the network and reduce our current high MVA spikes.

Reporting power outages

Please do not phone the After hours number or the Electrotechnical Department to report that you have no power immediately after Loadshedding is scheduled to be lifted. Please be aware of the rotational switching on, and wait at least 30 minutes before reporting no power. The directorate will be aware if there has been a possible substation trip that needs to be sorted out.

 

Issued by George Municipal Communications Department

Office of the Municipal Manager

#Eskom load shedding schedule – 8 March 2023

#Eskom load shedding due to the return of a generating unit each at Kriel, Majuba and Matimba power stations, Stage 5 loadshedding will not be implemented today as previously communicated.  Stage 4 loadshedding will continue to be implemented until further notice. Please continue using electricity sparingly.

#Eskom Load shedding update: 8 March 2023* Issued by George Municipality on behalf of Eskom*_

*George will be affected as follows:*

Wednesday 08/03/2023

12:00 – 14:30

20:00 – 22:30

Thursday 09/03/2023

02:00 – 04:30

10:00 – 12:30

18:00 – 20:30

Friday 10/03/2023

02:00 – 04:30

10:00 – 12:30

18:00 – 20:30

UNIONDALE NOW USES MISGUND LOAD SHEDDING SCHEDULE TEMPORARILY

*As of 3 March 2023, Eskom is feeding Uniondale power supply from a different region.

Uniondale’s loadshedding schedule now falls under Misgund.We advise consumers to consider the George Municipal issued load shedding schedules as the correct version. According to Eskom, this is a temporary arrangement which should only last approximately a week.*

*The load shedding Applications (Apps) that are in circulation may have not been updated about this change and will give incorrect information unintentionally. The George Municipality load shedding schedule remains accurate and reliable.*

*The latest load shedding schedule for Uniondale is as follows:*

Wednesday 08/03/2023

11:00 – 13:30

19:00 – 21:30

Thursday 09/03/2023

01:00 – 03:30

09:00 – 11:30

17:00 – 19:30

Friday 10/03/2023

01:00 – 03:30

09:00 – 11:30

17:00 – 19:30

SWITCHING ON AFTER LOADSHEDDING – Not all areas will be switched back on at the same time!

Residents of George must please note that with the extended load-shedding, our Electrotechnical Directorate is no longer able to switch the entire city back on at the same time. Our daily notifiable demand from ESKOM has historically been set at 85MVA and on average George would use between 60 and 80MVA, although the municipality must pay ESKOM for 85MVA.

If the power is returned simultaneously to all areas when load-shedding ends, this creates a massive spike or surge in power with all geysers, freezers/fridges/batteries etc drawing power at the same time. With the extended four-hour load-shedding, the spikes for George are consistently reaching 105 – 112 MVA.

Areas will be switched on in sections, on rotation after Load-shedding.

Eskom has indicated that unless George can reduce the spikes, they will increase our notifiable demand to the highest actual usage level which will in turn increase the purchase cost to the municipality. Consumers are requested to use electricity very sparingly when power returns after load-shedding (especially a 4-hour slot).

The municipality will now in rotation, switch the power on in sections. This means if for example the load-shedding slot is scheduled from 20h00 – 22h30, there is a chance that your area may only come on at 22h45 or 23h00.

Please do not switch high-usage equipment on immediately after Load-shedding.

Consumers are therefore urged to turn off high-usage equipment and where possible to not switch on appliances such as stoves and kettles for at least 30 minutes after load shedding. This will reduce the risk of overload tripping on the network and reduce our current high MVA spikes.

Reporting power outages

Please do not phone the After hours number or the Electrotechnical Department to report that you have no power immediately after Loadshedding is scheduled to be lifted. Please be aware of the rotational switching on, and wait at least 30 minutes before reporting no power. The directorate will be aware if there has been a possible substation trip that needs to be sorted out.

Issued by George Municipal Communications Department

Office of the Municipal Manager

Premier’s 2nd Energy Digicon hosts Mayor of George on their energy resilience initiatives

Premier’s 2nd Energy Digicon hosts Mayor of George on their energy resilience initiatives

On Thursday, 09 March 2023 Premier Alan Winde will host his second Energy Digicon. He will be joined by Executive Mayor of George Alderman Leon van Wyk, who will speak about how the George municipality is working towards becoming energy resilient.

Date: Thursday, 09 March 2023
Time: 11:15 am – 12:00 pm
Venue: Virtual platform Teams

Members of the public who would like to watch the Energy Digicon can watch live on the Premier’s and George Municipality’s social media pages:

PREMIER’S SOCIAL MEDIA PAGES
Youtube: https://www.youtube.com/@premieralanwinde6012
Facebook: https://www.facebook.com/windealan
Twitter: https://twitter.com/alanwinde

GEORGE MUNICIPALITY’S SOCIAL MEDIA PAGES
Twitter: www.twitter.com/@george_mun
Facebook: www.facebook.com/@george.municipality
Mayor Leon Van Wyk Facebook: www.facebook.com/@1stForGeorge
YouTube: https://www.youtube.com/@georgemunicipalofficialyou405/videos

The Digicon will also be recorded and will be available on the Premier’s YouTube channel.

Watch a recording of last week’s Digicon:

https://www.youtube.com/watch?v=U4duyXoJJyU

 

GARDEN ROUTE DAM LEVEL – Water Restrictions remain in place

Percentage storage at new raised dam wall height                    78,07
Rainfall for last 7 days:                                                                   55.4 mm
(Measured up to and including 6 March 2023)

The co-operation of all users of municipal water is essential and is greatly appreciated.

Follow this link for the detailed Stricter Water Restrictions in English/Afrikaans and Isixhosa.
https://www.george.gov.za/george-doc-categories/public-notices/general/

Contraventions of the Water Restrictions can be reported on 0800 424477.
Report water leaks and burst pipes to 044 801 9262/66 or after hours at 044 801 6300, as soon as you notice them.

*#Eskom Load shedding update: 6 March 2023*

*#Eskom Load shedding update: 6 March 2023*

_*Following the failure of five generating units today, Stage 5 loadshedding will be implemented from 16:00 today(Monday) until 05:00 tomorrow, Tuesday, whereafter Stage 4 loadshedding will resume until further notice. Issued by George Municipality on behalf of Eskom*_

 

*George will be affected as follows:*

Monday 06/03/2023

20:00 – 22:30

Tuesday 07/03/2023

04:00 – 06:30

12:00 – 14:30

20:00 – 22:30

Wednesday 08/03/2023

04:00 – 06:30

12:00 – 14:30

20:00 – 22:30

Thursday 09/03/2023

02:00 – 04:30

10:00 – 12:30

18:00 – 20:30

Friday 10/03/2023

02:00 – 04:30

10:00 – 12:30

18:00 – 20:30

 

UNIONDALE NOW USES MISGUND LOAD SHEDDING SCHEDULE TEMPORARILY

*As of 3 March 2023, Eskom is feeding Uniondale power supply from a different region.

Uniondale’s loadshedding schedule now falls under Misgund.We advise consumers to consider the George Municipal issued load shedding schedules as the correct version. According to Eskom, this is a temporary arrangement which should only last approximately a week.*

*The load shedding Applications (Apps) that are in circulation may have not been updated about this change and will give incorrect information unintentionally. The George Municipality load shedding schedule remains accurate and reliable.*

*The latest load shedding schedule for Uniondale is as follows:*

Monday 06/03/2023

19:00 – 21:30

Tuesday 07/03/2023

03:00 – 05:30

11:00 – 13:30

19:00 – 21:30

Wednesday 08/03/2023

03:00 – 05:30

11:00 – 13:30

19:00 – 21:30

Thursday 09/03/2023

01:00 – 03:30

09:00 – 11:30

17:00 – 19:30

Friday 10/03/2023

01:00 – 03:30

09:00 – 11:30

17:00 – 19:30

SWITCHING ON AFTER LOADSHEDDING – Not all areas will be switched back on at the same time!

Residents of George must please note that with the extended load-shedding, our Electrotechnical Directorate is no longer able to switch the entire city back on at the same time. Our daily notifiable demand from ESKOM has historically been set at 85MVA and on average George would use between 60 and 80MVA, although the municipality must pay ESKOM for 85MVA.

If the power is returned simultaneously to all areas when load-shedding ends, this creates a massive spike or surge in power with all geysers, freezers/fridges/batteries etc drawing power at the same time. With the extended four-hour load-shedding, the spikes for George are consistently reaching 105 – 112 MVA.

Areas will be switched on in sections, on rotation after Load-shedding.

Eskom has indicated that unless George can reduce the spikes, they will increase our notifiable demand to the highest actual usage level which will in turn increase the purchase cost to the municipality. Consumers are requested to use electricity very sparingly when power returns after load-shedding (especially a 4-hour slot).

The municipality will now in rotation, switch the power on in sections. This means if for example the load-shedding slot is scheduled from 20h00 – 22h30, there is a chance that your area may only come on at 22h45 or 23h00.

Please do not switch high-usage equipment on immediately after Load-shedding.

Consumers are therefore urged to turn off high-usage equipment and where possible to not switch on appliances such as stoves and kettles for at least 30 minutes after load shedding. This will reduce the risk of overload tripping on the network and reduce our current high MVA spikes.

Reporting power outages

Please do not phone the After hours number or the Electrotechnical Department to report that you have no power immediately after Loadshedding is scheduled to be lifted. Please be aware of the rotational switching on, and wait at least 30 minutes before reporting no power. The directorate will be aware if there has been a possible substation trip that needs to be sorted out.

 

Issued by George Municipal Communications Department

Office of the Municipal Manager

UNIONDALE NOW USES MISGUND LOAD-SHEDDING SCHEDULE TEMPORARILY

UNIONDALE NOW USES MISGUND LOAD-SHEDDING SCHEDULE TEMPORARILY

As of 3 March 2023, Eskom is feeding Uniondale power supply from a different region.

Uniondale’s load-shedding schedule now falls under Misgund. We advise consumers to consider the George Municipal issued load shedding schedules as the correct version.

According to Eskom, this is a temporary arrangement which should only last approximately a week.

The load shedding Applications (Apps) that are in circulation may have not been updated about this change and will give incorrect information unintentionally. The George Municipality load-shedding schedule remains accurate and reliable.

The latest load-shedding schedule for Uniondale is as follows:

Monday 06/03/2023
03:00 – 05:30
11:00 – 13:30
19:00 – 21:30

Tuesday 07/03/2023
03:00 – 05:30
11:00 – 13:30
19:00 – 21:30

Wednesday 08/03/2023
03:00 – 05:30
11:00 – 13:30
19:00 – 21:30

Thursday 09/03/2023
01:00 – 03:30
09:00 – 11:30
17:00 – 19:30

Friday 10/03/2023
01:00 – 03:30
17:00 – 19:30

Issued by George Municipality
5 March 2023

*

UNIONDALE GEBRUIK MISGUND BEURTKRAG-SKEDULE TYDELIK

Vanaf 3 Maart 2023 voer Eskom Uniondale kragtoevoer uit ‘n ander streek.

Uniondale se beurtkrag-skedule val nou onder Misgund. Ons raai verbruikers aan om die George Munisipale uitgereikte beurtkragskedules as die korrekte weergawe te oorweeg.

Volgens Eskom is dit ‘n tydelike reëling wat net ongeveer ‘n week behoort te duur.

Die beurtkrag-toepassings (toepassings) wat in omloop is, is moontlik nie oor hierdie verandering opgedateer nie en sal onbedoeld verkeerde inligting verskaf. Die George-munisipaliteit se beurtkragskedule bly akkuraat en betroubaar.

Die jongste beurtkragskedule vir Uniondale is soos volg:

Maandag 06/03/2023
03:00 – 05:30
11:00 – 13:30
19:00 – 21:30

Dinsdag 07/03/2023
03:00 – 05:30
11:00 – 13:30
19:00 – 21:30

Woensdag 08/03/2023
03:00 – 05:30
11:00 – 13:30
19:00 – 21:30

Donderdag 09/03/2023
01:00 – 03:30
09:00 – 11:30
17:00 – 19:30

Vrydag 10/03/2023
01:00 – 03:30
17:00 – 19:30

Uitgereik deur George Munisipaliteit
5 Maart 2023