<<<<Sunday, 15 October 2023: Due to stable generation capacity with breakdowns at 13 158MW and planned maintenance at 6 051MW of generation capacity, loadshedding will remain suspended today until 16:00 on Monday. Thereafter, Stage 2 loadshedding will be implemented from 16:00 until 05:00 on Tuesday. Loadshedding will then be suspended from 05:00 until 16:00 and Stage 2 implemented from 16:00 until 05:00 on Wednesday. This pattern will be repeated daily until further notice. Eskom will communicate should any significant changes occur.(Eskom)>>>
George will be affected as follows:
Sunday 15/10/2023
None
Monday 16/10/2023
None
Tuesday 17/10/2023
None
Wednesday 18/10/2023
22:00 – 00:30
Thursday 19/10/2023
22:00 – 00:30
Friday 20/10/2023
None
Uniondale will be affected as follows:
Sunday 15/10/2023
None
Monday 16/10/2023
None
Tuesday 17/10/2023
17:00 – 19:30
Wednesday 18/10/2023
17:00 – 19:30
Thursday 19/10/2023
01:00 – 03:30
Friday 20/10/2023
01:00 – 03:30