Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

Eskom Stage 4 loadshedding will be implemented from 14:00 on Friday

Eskom Stage 4 loadshedding will be implemented from 14:00 on Friday until 05:00 on Saturday; thereafter Stage 2 loadshedding will continue until 05:00 on Monday, 8 November 2021.

George will be affected as follows:
Friday 05/11/2021
12:00 to 14:30
20:00 to 22:30

Saturday 06/11/2021
04:00 to 05:00
20:00 to 22:30

Sunday 07/11/2021
04:00 to 06:30

Monday 08/11/2021
04:00 to 05:00

Uniondale will be affected as follows:
Friday 05/11/2021
15:00 to 17:30
23:00 to 01:30

Saturday 06/11/2021
23:00 to 01:30

Sunday 07/11/2021
07:00 to 09:30

Monday 08/11/2021
None

Issued by George Municipality on 5 November 2021 at 13:40.