LOADSHEDDING UPDATE: 6 DECEMBER 2022
Tuesday, 06 December 2022: Stage 3 loadshedding will be implemented this afternoon at 16:00 – 05:00 tomorrow morning and on Wednesday afternoon at the same time. Stage 2 loadshedding will continue being implemented at 05:00 – 16:00 daily until further notice. Eskom will publish a further update as soon as there are any significant changes
George will be affected as follows:
Tuesday 06/12/2022
20:00 – 22:30
Wednesday 07/12/2022
04:00 – 06:30
20:00 – 22:30
Thursday 08/12/2022
04:00 – 06:30
12:00 – 14:30
Friday 09/12/2022
10:00 – 12:30
18:00 – 20:30
Uniondale will be affected as follows:
Tuesday 06/12/2022
15:00 – 17:30
23:00 – 01:30
Wednesday 07/12/2022
07:00 – 09:30
23:00 – 01:30
Thursday 08/12/2022
07:00 – 09:30
15:00 – 17:30
Friday 09/12/2022
13:00 – 15:30
21:00 – 23:30
VERY IMPORTANT PLEASE
ONLY USE ESSENTIAL APPLIANCES WHEN POWER IS RESTORED
Consumers are reminded to use electricity sparingly especially when power returns after load shedding. This will reduce the risk of overload tripping on the network. Consumers are requested, where possible to not switch on appliances such as stoves and kettles for at least 30 minutes after load shedding.