Upgrading of Roads, Sidewalks and Stormwater: Delville Park – Phase 3
The road rehabilitation and upgrade of stormwater infrastructure in Puma Street, and the construction of sidewalks in Puma and Antelope Streets, Delville Park, will impact residents and road users from September 2024 to February 2025.
The construction duration is estimated at 6 months.
PROJECT:
UPGRADING OF ROADS, SIDEWALKS AND STORMWATER INFRASTRUCTURE: DELVILLE PARK – PHASE 3
DESCRIPTION:
Road rehabilitation includes repairs to the base layers, surface layers, kerbs and channels.
Stormwater infrastructure upgrades include the construction of catch pits, manholes and sub-soil drains.
Sidewalks will be constructed on both sides of the road in Puma and Antelope Streets.
PROJECT PERIOD:
September 2024 to February 2025
SERVICE DISRUPTION:
Municipal services may be disrupted during construction. Advance notification of planned temporary disruptions will be sent out via social media.
WORKING HOURS:
Working hours will be from 07h00 to 18h00 Mondays to Fridays and 07h00 – 14h00 on Saturdays as may be needed occasionally.
TRAFFIC IMPACT:
Caution needs to be exercised by residents, road users and pedestrians throughout the duration of the construction period. Adherence to flag persons, temporary road signage and markings will be required. Sections of the road may be closed to the public, but access will be granted to residents.
ACCESS TO SITE:
Access to the site will be strictly controlled. Any member of the public who enters the site will have to comply with the relevant requirements in terms of the Health and Safety Act.
PROJECT ENQUIRIES: Mr Dawie Gerrits – 082 944 3654
The George Municipality apologises for any inconvenience and appeals to all residents to be patient and exercise caution during the upgrade. Please look out for and adhere to temporary road signage and roadworks personnel.