ESKOM LOADSHEDDING CHANGE IN STATUS, 19 October 2022 @ 17h31

Stage 3 loadshedding will be implemented at 16:00 on Wednesday and Thursday. In order to replenish the dam levels at the pumped storage stations, this load shedding will be extended until 05:00 (previously midnight). Similarly, Stage 2 loadshedding will be implemented at 16:00 on Friday and continue until 05:00 on Saturday.

George will be affected as follow

Wednesday 19/10/2022
22:00 – 00:30

Thursday 20/10/2022
22:00 – 00:30
04:00 – 05:30

Friday 21/10/2022
None

Uniondale will be affected as follows

Wednesday 19/10/2022
17:00 – 19:30

Thursday 20/10/2022
01:00 – 03:30

Friday 21/10/2022