Eskom loadshedding confirmed for week up until 25 July 2022
Eskom loadshedding confirmed: Stage 2 from 16h00 – 24h00 from 18 – 21 July 2022.
Stage 1 will start from 16h00 – 24h00 from 22 – 25 July 2022.
Issued by George Mun 18 July 2022 at 14h50
George will be affected as follows:
Monday 18/07/2022
22:00 to 00:30
Tuesday 19/07/2022
22:00 to 00:30
Wednesday 20/07/2022
None
Thursday 21/07/2022
None
Friday 22/07/2022
20:00 to 22:30
Saturday 23/07/2022
None
Sunday 24/07/2022
None
Monday 25/07/2022
None
Uniondale will be affected as follows:
Monday 18/07/2022
17:00 to 19:30
Tuesday 19/07/2022
None
Wednesday 20/07/2022
None
Thursday 21/07/2022
16:00 to 17:30
Friday 22/07/2022
23:00 to 00:30
Saturday 23/07/2022
None
Sunday 24/07/2022
None
Monday 25/07/2022
None