ESKOM LOADSHEDDING UPDATE – 3 December 2023

In order to manage emergency reserves, Stage 4 loadshedding will remain in force until 05:00 on Monday.   Thereafter, Stage 3 loadshedding will be implemented from 05:00 until 16:00, followed by Stage 4 loadshedding until 05:00 on Tuesday.  This pattern of Stage 3 loadshedding in the morning and Stage 4 loadshedding in the evening will be repeated daily until Friday 16:00. Eskom will communicate should any significant changes occur. Unplanned outages are at 12 648MW and planned maintenance is at 6 814MW of generation capacity.

 

George will be affected as follows:

Sunday 03/12/2023

22:00 – 00:30

 

Monday 04/12/2023

06:00 – 08:30

14:00 – 16:30

22:00 – 00:30

 

Tuesday 05/12/2023

04:00 – 06:30

12:00 – 14:30

20:00 – 22:30

 

Wednesday 06/12/2023

04:00 – 05:00

12:00 – 14:30

20:00 – 22:30

 

Thursday 07/12/2023

04:00 – 06:30

20:00 – 22:30

 

Friday 08/12/2023

04:00 – 06:30

12:00 – 14:30

20:00 – 22:30

 

Uniondale will be affected as follows:

Sunday 03/12/2023

17:00 – 19:30

 

Monday 04/12/2023

01:00 – 03:30

09:00 – 11:30

17:00 – 19:30

 

Tuesday 05/12/2023

07:00 – 09:30

15:00 – 17:30

23:00 – 01:30

 

Wednesday 06/12/2023

15:00 – 17:30

23:00 – 01:30

 

Thursday 07/12/2023

07:00 – 09:30

16:00 – 17:30

23:00 – 01:30

 

Friday 08/12/2023

07:00 – 09:30

15:00 – 17:30

23:00 – 01:30

 

Issued George Municipality on behalf of ESKOM