Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

Eskom Stage 3 loadshedding implemented – updated 27/12/2022

*Eskom Stage 3 loashedding will be implemented from 16:00 today until 05:00 tomorrow morning. This will be repeated everyday for the remainder of the week. Stage 2 loadshedding will be implemented from 05:00 tomorrow morning until 16:00. Issued by George Municipality on behalf on Eskom, Tuesday, 27 December 2022 at 12h30*
 
-*George will be affected as follows:*_
Tuesday 27/12/2022
18:00 – 20:30
 
Wednesday 28/12/2022
02:00 – 04:30
18:00 – 20:30
 
Thursday 29/12/2022
00:00 – 02:30
08:00 – 10:30
 
Friday 30/12/2022
00:00 – 02:30
08:00 – 10:30
16:00 – 18:30
 
Saturday 31/12/2022
16:00 – 18:30
 
Sunday 01/01/2023
14:00 – 16:30
22:00 – 00:30
 
_*Uniondale will be affected as follows:*_
 
Tuesday 27/12/2022
21:00 – 23:30
 
Wednesday 28/12/2022
05:00 – 07:30
21:00 – 23:30
 
Thursday 29/12/2022
03:00 – 05:30
11:00 – 13:30
 
Friday 30/12/2022
03:00 – 05:30
11:00 – 13:30
19:00 – 21:30
 
Saturday 31/12/2022
19:00 – 21:30
 
Sunday 01/01/2023
17:00 – 19:30