REPAIRS TO ROAD SLIP FAILURES, WHITES ROAD, WILDERNESS
The repairs to road slip failures will have an impact on residents, pedestrians,
runners, cyclists and road users. Construction will commence in August 2024. The estimated construction duration is 2 months.
PROJECT:
REPAIRS TO ROAD SLIP FAILURES ALONG WHITES ROAD, WILDERNESS
DESCRIPTION
The purpose of this Contract is to repair two road slip failures along Whites Road, Wilderness. The works comprises of the installation of retaining structures and repairs to the roadway and drainage system
PROJECT PERIOD
• PHASE 1: 5 – 30 AUGUST 2024 (FULL ROAD CLOSURE)
• PHASE 2: 02 SEPTEMBER 2024 TILL 04 OCTOBER 2024 (STOP & GO SYSTEM)
SERVICE DISRUPTION
No Municipal services will be affected. Road lane closures will be implemented along the affected areas. The Contractor will liaise with affected residents in advance, to arrange local access where and when required.
WORKING HOURS
Working hours will be from 07h00 to 18h00 Mondays to Fridays, and potentially from
07h00 to 14h00 on Saturdays.
IMPACT
The construction area will be fully closed to the public. No pedestrians, runners or cyclists may access the construction area throughout the duration of the construction period.
Flag persons and temporary road signage must be adhered to at all times.
ACCESS TO SITE
Access to the construction site will be strictly controlled. No member of the public will be allowed access to the construction area, in terms of the Occupational Health and Safety Act.
The George Municipality apologises for any inconvenience and appeals to the public to be patient and exercise caution throughout the construction period. Please look out for all temporary road signage and construction personnel