Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

Author: Nadine Payle

Urhwebo e-Transand grades emergency airstrip

George Fire Chief Neels Barnard had high praise and special thanks for Urhwebo e-Transand who recently graded and levelled the landing strip at the Denneoord Emergency Airbase at no cost to the municipality. The emergency airbase which was established in 2017 remains the Garden Route’s first dedicated emergency firefighting airstrip on municipal property.

Caption: Seen here standing on the newly levelled landing strip are from left, Lemar Meyer (Urhwebo e-Transand), Chief Fire Officer Neels Barnard, Sandisile Linton (Urhwebo e-Transand), Brandon van Rensburg (Urhwebo e-Transand) and Louw van de Merwe (Kishugu Pilot)

The airbase a collaborative project between George Municipality, Southern Cape Fire Protection Association, Working on Fire and Garden Route District Municipality has meant that firefighting planes can respond much faster than they would have been able if they were stationed at a commercial airport where they would have had to wait in line for a runway along with other aircraft. This is especially applicable during the summer fire season which coincides with the very busy holiday season when thousands of flights are scheduled at commercial airports.

Three fixed wing spotters, two fixed wing bombers and a chopper are stationed at the base during the fire season, and usually at least one plane and a chopper out of season. Municipalities in the Garden Route district use the facility on a call-out basis as services are required. The airbase consists of a runway, helipad, firebase, hangars, taxiways, and a water refilling point.

 

After-hours Assistance for Blocked Pre-Paid Electricity Meters to be discontinued from July 2024

Effective July 2024, after-hours assistance for blocked pre-paid electricity meters will no longer be available. Therefore, arrangements to unblock a meter must be made before Friday afternoons at 14:00.

Once all credit control actions (such as SMS notifications and final demand notices) have been implemented and no response is received from the client, a one-time block for R300.00 will be instituted on arrear accounts. This means that the account holder can incur up to 10 transactions to the maximum value of R300. After reaching the R300 limit or completing 10 transactions, the meter will be fully blocked with no further purchases allowed and unblocking arrangements will need to be attended to during the week.

If you buy 10 times for R10.00 or R20.00 your meter will be blocked before you reach the R300.00 limit due to the 10-transaction cap.

To UNBLOCK your prepaid meter, follow one of the steps below:

• Full payment of your municipal account
• Payment arrangement
• Apply for Indigent Subsidy if you qualify (2 x SASSA)

For assistance, contact the Municipality’s Credit Control section during office hours at 044 801 9111 or email creditcontrol@george.gov.za

*******************************************************

Na-ure bystand vir geblokte pre-paid meters word vanaf Julie 2024 gestaak
Met ingang van Julie 2024 sal die na-ure bystand vir geblokkeerde pre-paid meters nie meer beskikbaar wees nie. Enige reelings om ’n blok te lig moet dus geskied voor Vrydag-middae om14:00.

Wanneer alle kredietbeheeraksies (soos SMS-kennisgewings en finale kennisgewings) geïmplementeer is en geen reaksie van die kliënt ontvang is nie, sal ‘n eenmalige blok vir R300.00 op agterstallige rekeninge ingestel word. Dit beteken dat die rekeninghouer tot 10 transaksies kan aangaan, tot ’n maksimum van R300 om krag te koop. Nadat die R300-limiet bereik is of 10 transaksies voltooi is, sal die meter ten volle geblok word en geen verdere aankope sal toegelaat word en ontblokkeringsreëlings sal gedurende die week gedoen moet word.

As daar dus 10 keer krag gekoop word vir R10.00 of R20.00 sal die meter geblok word voordat die R300.00 limiet bereik is as gevolg van die 10-transaksielimiet.

Om ’n geblokte pre-paid meter te ontblok volg asseblief een van die volgende stappe hieronder.

• Volle betaling van u munisipale rekening
• Afbetalingsreeling
• Doen aansoek om deernis subsidie indien u kwalifiseer (2 x SASSA)

Vir bystand, kontak die Munisipaliteit se Kredietbeheerafdeling gedurende kantoorure by 044 801 9111 of e-pos creditcontrol@george.gov.za

*************************************************************

Uncedo lwasemva kweeyure zomsebenzi lwee-Akhawunti eziValiweyo Luyekiwe ukususela kweyeKhala 2024

Ukuqala kweyeKhala 2024, uncedo lwasemva kweeyure zomsebenzi kwii-akhawunti ezivaliweyo alusayi kuphinda lufumaneke.

Akuba onke amanyathelo olawulo lwamatyala (afana nezaziso zeSMS, kunye nezaziso zebango lokugqibela) ephunyeziwe kwaye kungekho mpendulo ifunyenweyo evela kumxhasi, ukuvulwa kombane ovaliweyo ngenyoba enye yokuthenga umbane ukuya kuma kuma-R300.00 kuya kuqaliswa kwii-akhawunti ezisemva ngentlawulo. Oku kuthetha ukuba umnini-akhawunti angathenga umbane ukuyokutsho kwi-10 lezihlandlo kwelona xabiso liphezulu lama-R300. Emva kokufikelela kumda wama-R300 okanye ukugqiba izihlandlo zentengo ezili-10, imitha yombane iya kuvalwa ngokupheleleyo kungasayi kuphinda kuthengwe kwaye amalungiselelo okuvula kuya kufuneka enziwe Phakathi evekini.

Ukuba uthenga izihlandlo ezili-10 nge-R10.00 okanye nge-R20.00 imitha yakho iya kuvaleka phambi kokuba ufikelele kuma-R300.00 eqingqiweyo ngenxa yomlinganiselo wezihlandlo ezili-10 zokuthenga.

Ngaba ufuna UKUVULA isixhobo sakho sokulinganisa umbane ohlawulelwa kwangaphambili? Thabatha elinye lala manyathelo alandelayo:
• Hlawula i-akhawunti yakho kamasipala ngokupheleleyo
• Yenza amalungiselelo entlawulo
• Faka isicelo seNkxaso-mali yabangathathintweni ukuba ufanelekile (2 x SASSA)

Malunga noncedo, qhagamshelana necandelo lolawulo lwamatyala kamasipala ngamaxesha omsebenzi ku- 044 801 9111 okanye nge-imeyili ku creditcontrol@george.gov.za

Planned Water Interruption, Groeneweide Park

NOTIFICATION OF THE INTERRUPTION OF THE POTABLE WATER SUPPLY.

THE FOLLOWING AREAS WILL BE AFFECTED:
Groeneweide Park, Gwaing, George Airport, Oubaai, Breakwater Bay and Herold’s Bay

NOTICE is hereby given that the water supply will be interrupted on 23 JULY 2024 FROM 09H00 TO 16H30 for the purpose of doing alterations to the water mains.
Should circumstances prevent the work being carried out during the abovementioned period; the work will be done on 24 JULY 2024 FROM 09H00 TO 16H30

*****************************
KENNISGEWING VAN DIE ONDERBREKING VAN DIE GESUIWERDE WATER TOEVOER.

DIE VOLGENDE AREAS SAL GERAAK WORD:
Groeneweide Park, Gwaing, George Lughawe, Oubaai, Breakwater Bay en Heroldsbaai

KENNISGEWING geskied hiermee dat die water toevoer onderbreek sal word op 23 JULIE 2024 VANAF 09H00 TOT 16H30 met die doel om veranderings aan water hoofleidings te maak.
Sou omstandighede verhoed dat die werk gedoen kan word gedurende bogenoemde tydperk, sal die werk gedoen word op 24 JULIE 2024 VANAF 09H00 TOT 16H30

URGENT NOTICE: CONSTRUCTION OF A NEW PACALTSDORP WEST RESERVOIR- WORKING SATURDAY

A planned construction of the New Pacaltsdorp (West) 14,5ML Reservoir, & Pump station, initially scheduled to take place on weekdays, will also include tomorrow, Saturday, 20 July 2024 between 07:00 and 14:00.

SERVICE DISRUPTION:
Minor operational interruptions can be expected during the construction works. Advance notification of planned temporary disruptions and the effects thereof will be issued via social media.

TRAFFIC IMPACT:
Residents, road users and pedestrians need to exercise caution throughout the construction period. Please adhere to flag persons, temporary construction works and road signage.

ACCESS TO SITE:
Access to the site will be strictly controlled. No member of the public will be allowed access to the construction area, in terms of the Occupational Health and Safety Act.

PROJECT ENQUIRIES:

Mr Andre Scheepers – 044 801 9492 (Technical)
Mr Alewijn Dippenaar – 082 457 5675 (Public Liaison Officer)

The George Municipality apologises for any inconvenience and appeals to the public to be patient and exercise caution throughout the construction period. Thank you for your understanding and cooperation.

UPDATE: Unplanned Power Outage: George Industria and Levalia

All power supply has now been restored to all the affected areas.

Should you still experience a shortage of power supply, please contact the Electro Department on:

Electrotechnical Services Office Switchboard: 044 801 9222 (7.45 – 4.30pm)
Electrotechnical Customer Care: 044 801 9202/9258
New WhatsApp Number 067 350 3295
(Available Monday to Friday 7.45 – 4.30pm)

George Municipality thanks its residents of George for their patience.

UPDATE: Water Main Line Damage in Blue Mountain Area

UPDATE: Water Main Line Damage in Blue Mountain Area
Issued by George Municipality, 18 July 2024 @ 16:40

The repair has been completed, and the water supply has been restored to the Blue Mountain area and surrounding areas.

Thank you for your patience and understanding.

Planned Power Outage: A Portion of George CBD, Memorium Street

NOTIFICATION OF THE INTERRUPTION OF THE ELECTRICITY SUPPLY.

THE FOLLOWING AREAS WILL BE AFFECTED: A PORTION OF GEORGE CBD, MEMORIUM STREET.

NOTICE is hereby given that the electricity supply will be interrupted on MONDAY 22 JULY 2024 FROM 09H00 TO 16H00 for the purpose of doing alterations to the electrical mains. Consumers are warned to treat the installation as being live for the full duration as the supply may be resumed at any time within the notified period.
Should circumstances prevent the work from being carried out during the abovementioned period; the work will be done on TUESDAY 23 JULY 2024 FROM 09H00 TO 16H00

***********************************************************************

KENNISGEWING VAN DIE ONDERBREKING VAN DIE ELEKTRIESE TOEVOER. DIE VOLGENDE AREAS SAL GERAAK WORD: GEDEELTE VAN GEORGE CBD, MEMORIUM STRAAT.

KENNISGEWING geskied hiermee dat die elektriese toevoer onderbreek sal word op MAANDAG 22 JULIE 2024 VANAF 09H00 TOT 16H00 met die doel om veranderings aan elektriese hoofleidings te maak. Klante word gewaarsku om die installasie as lewendig te beskou vir die volle periode aangesien die toevoer enige tyd gedurende die periode aangeskakel mag word.

Sou omstandighede verhoed dat die werk gedoen kan word gedurende bogenoemde periode, sal die werk gedoen word op DINSDAG 23 JULIE 2024 VANAF 09H00 TOT 16H00

Water Main Line Damage in the Blue Mountain Area

A contractor has damaged a potable water main line in the Blue Mountain area. George Municipality teams are en route to investigate and resolve the issue.

The estimated time of repair will be provided as more information becomes available.

Currently, Blue Mountain experiences low pressure and is without water in some parts. Surrounding areas that may be affected include Kraaibosch, Levallia, Rosemore, Garden Route Mall, Eden Meander, and Protea Park.

We apologise for the inconvenience and appreciate your patience as we work to restore water service.

Further updates will be communicated as they become available.

UPDATE: Telephone Lines Down at Electro-Technical Department & Civils Depot

We regret to inform you that our telephone lines and email communications remain offline at our electro-technical department, Civil Engineering Services (CES) Depot, and Customer Care due to technical issues with our internet connection.

Electro Tech alternative number
For your convenience, please use our Whatsapp line on 067 350 3295, available from Monday to Friday (7.45 – 4.30pm)

Sewerage & Water Services
For all Sewerage and Water related matters., please contact our Whatsapp line on 066 111 5986, only available between 7.45 – 4.30pm.

Stormwater Services
For all stormwater-related matters, please contact our Whatsapp line on 066 111 5943, only available between 7.45 – 4.30pm.

The Technical staff and Service Provider are currently attending to it. We apologise for the inconvenience caused.

Media Statement: Updated status on the BFI Water Projects for George

George Municipality received a Budget Facility for Infrastructure Funding (BFI) grant to the value of R1.115 billion from National Treasury in the 2021/22 financial year and the BFI project with its various project components, has shown significant progress and expenditure up to the 2023/24 financial years. The full BFI project is planned to be completed by October 2025.

George Municipality is actively working to keep our economy on the go, by ensuring adequate long-term planning and investment into our resources – that is water, sewerage and electricity. The Municipality currently provides water services to over 294 929 residents from 85 931 households across 28 wards including the coastal areas of Kleinkrantz, Wilderness, Victoria Bay, Herold’s Bay and Gwaing in the city of George area as per STATSSA 2022. The objectives of the project are to ensure adequate potable water supply to meet the demand of the current population and to provide security for future development, both social and economic, as well as to reduce pollution of certain main water courses.

The project consists of 12 components, some of which will be executed in more than one construction phase.

Component 1 and 2
The 20 Mℓ/d extension to the New Water Treatment Works (New WTW) is component 2 and component 1 is the new WTW Residuals Treatment facility of the project.

Status: The first contract, valued at R263 million, for the civil engineering works – construction is nearing completion. The tender for the mechanical, electrical and instrumentation (MEI) works to the value of R217 million – the installation on site is progressing at pace. Components 1 and 2 form the largest sub-projects of the overall BFI project.

A number of plant shutdowns are required at the new Water Treatment Works to enable tie-ins on the raw water feed to the plant, the clear water feed from the plant to the reservoirs, valve chamber construction, injection chamber construction and some refurbishment of pipework in the existing new Water Treatment Works. These shutdowns have to be carefully co-ordinated to avoid unnecessary downtime or reduction in water supply to George and also contributes to the requirement for the continued water restrictions due to the inability to supply treated water in larger quantities.

The civil engineering construction was scheduled for completion at the end of February 2024 and the mechanical, electrical and instrumentation by December 2024. The latter is still true for the MEI contract, but additional work required on the raw water pipeline and intake works extended the completion date of the civil works. The civil construction Practical Completion dates are as follows:

Portion 1 – Modifications to existing works: Scheduled for 24 June 2024
Portion 2 – Main works 20 Mℓ/d plant: Scheduled for 24 June 2024
Portion 3A – Residuals facility: 26 Mar 2023
Portion 3B – Residuals facility: 20 March 2024
Portion 4 – New clear water pipeline: 20 Dec 2023

Component 3
The refurbishment of the existing Sludge Discharge System Phase 1 and 2 at the Eden, Meul and Schaapkop Pumpstations will improve the reliability of the aged pump stations.

Status: Construction of the first phase has reached completion at the Meul and Eden Pump Stations
• Phase 1: The first phase of the upgrading and refurbishment of the Meul Sewage Pumpstation was completed in June 2023, including a new standby generator and motor control centre. This is also the case for the new motor control centre at the Eden Sewage Pumpstation. The Schaapkop Sewage Pumpstation implementation was delayed and the tender for the Phase 1 implementation had to be cancelled.

•Phase 2: Civil engineering construction on the Meul Sewage Pumpstation Phase 2, as well as the Eden Pump Station have been awarded. While construction at Eden Ps is being delayed by a DFFE permit, the construction at Meul Pump Station has reached Practical Completion. The contract for Mechanical, Electrical and Instrumentation works at Meul Pump Station has also been awarded and construction is due to start. Similarly, the tenders for both portions under the Schaapkop Pump Station have been awarded, incorporating both Phases 1 and 2 to be implemented as a single project.

Component 4
The upgrading of the Garden Route Dam Outlet and Supply project includes the replacement of the existing 600 mm diameter raw water pipeline from the intake tower at the Garden Route Dam to the raw water pumpstations, with a new 800 mm diameter stainless steel pipeline to accommodate a higher flowrate in accordance with the future raw water flow requirements.

Status: The project construction contract was awarded for an amount of R 34.2 million in May 2023. Construction progress is currently at 70%. The estimated completion date for the project is October 2024.

Component 5 – COMPLETED
2 x 1250 kVA generators have been installed at the Garden Route Dam raw water pumpstation. These generators will ensure that during loadshedding or any other power outage, raw water can continue to be pumped uninterrupted to the Water Treatment Works for processing for drinking water supply.

Status:
Construction and installation have been completed and the project has been commissioned. The generators automatically start and can operate during load-shedding.

Component 6
An additional 40 million litre raw water storage and balancing dam will be constructed, as well as a 340m long 800mm diameter raw water outlet pipeline and an 1000mm diameter raw water pump main extension, to secure sufficient raw water storage capacity to supply the 20Mℓ/day extension to the Water Treatment Works and the existing two treatment plants. The new raw water dam will supplement the existing storage dams that provide raw water to the two water treatment plants.

Status: The project construction contract was awarded for an amount of R 93,1 million in December 2023. Construction commenced on site in May 2024 after receiving all statutory approvals. Construction progress is currently at 10%. The estimated completion date for the project is August 2025.

Component 7 – COMPLETED
The rehabilitation of the Old Water Treatment Works, located in Denneoord will allow for the refurbishment of the 20 Mℓ/d treatment plant.

Status: This component consists of four separate contracts and the tenders were awarded at the beginning of 2022. All work has been completed under this component.

Component 8
Refurbishment of the Kaaimans River Pumpstation equipment will include the installation of six (6) new submersible vortex impeller pumps in the sump, a strainer system and six new high lift centrifugal pumps and includes the replacement of the electrical control equipment. The Kaaimans Pumpstation discharges into the Garden Route Dam and contributes significantly to the George raw water resource requirements.

Status: The project construction contract was awarded for an amount of R 16.5 million IN June 2023. Construction progress is currently at 80%. The estimated completion date for the project is August 2024.

Component 9
The new 14,5 Mℓ Pacaltsdorp West Reservoir and Pumpstation will address the current inadequate emergency and balancing potable water storage and provide adequate water security for the medium-term future developments in the western area of Pacaltsdorp.

Status: The project construction contract was awarded for an amount of R 106,9 million in January 2024. Construction commenced on site in May 2024 after receiving all statutory approvals. Construction progress is currently at 10%. The estimated completion date for the project is October 2025.

Component 10
The new 3 Mℓ Pacaltsdorp East Reservoir, 300 kl Tower and pumpstation will address the inadequate emergency and balancing potable water storage in the eastern area of Pacaltsdorp.

Status: The project construction contract was awarded for an amount of R 59,9 million in December 2023. Construction commenced on site in May 2024 after receiving all statutory approvals. Construction progress is currently at 11%. The estimated completion date for the project is July 2025.

Component 11
A new pumpstation and control valves will be provided at the existing Thembalethu West Reservoir and Tower and an existing bulk supply pipeline will be upgraded to ensure adequate potable water storage and increased security of potable water supply to the western area of Thembalethu, as well as provide capacity to meet future development water demands.

Status: Two construction contracts were awarded for a total amount of R 23,9 million in December 2023 and March 2024. Construction commenced on site in May 2024 after receiving all statutory approvals. Construction progress is currently at 7%. The estimated completion date for the project is November 2024.

Component 12
A new 8 Mℓ Thembalethu East Reservoir, 1000 kl Tower and Pumpstation will be provided to ensure adequate potable water storage and increased security of potable water supply to the eastern area of Thembalethu, as well as provide capacity to meet future development water demands.

Status: The project construction contract was awarded for an amount of R 106,5 million in February 2023. Construction commenced on site in April 2024. Construction progress is currently at 10%. The estimated completion date for the project is June 2025.

PUBLIC NOTICE: Early Closure of MVR, DLTC and VTS offices

Please be advised that Motor Vehicle Registration (MVR) Hibernia, MVR Blanco, Driving Licence Testing Centre (DLTC) in Pacaltsdorp, and Vehicle Testing Station (VTS) will be closed from 2 pm on Wednesday, 17 July 2024.

All services will resume as normal on 18 July 2024.

Emergency Electrical Repair Work: Heather Park

An emergency repair will be conducted on Rooiels Avenue in Heather Park.
The estimated duration for the repair is 4 hours.

Thank you for your cooperation and understanding during this essential maintenance work.

UPDATE 10: Inclement Weather and Emergency Incidents in George

Issued by George Municipality, 12 July 2024 @ 16:45

The George Municipality continues addressing various power outages and the cleanup of fallen trees. Currently, no roads are closed. Our emergency personnel is on standby with high winds and wave heights exceeding 4 metres expected for the weekend.

WEATHER WARNING

A Yellow Level 2 Warning affecting George has been received from the South African Weather Service (SAWS). A cold front associated with a steep upper air trough is expected to result in strong to near gale westerly to north-westerly winds (40 to 60 km/h between Table Bay and Plettenberg Bay on Sunday, 14 July 2024. Wave heights of 3 to 4.56 metres are expected from Saturday, 13 July 2024 morning while the winds are only expected from the afternoon.

POWER OUTAGES

Parts of George are experiencing power outages due to bad weather. Electrical teams are dispatched to various areas:
• Bergstraat and Watsonia Line, Wilderness Heights – Repairs ongoing
• De Waal Drive – Restored
• Portion of Zone 4 and Zone 5 in Thembalethu – Restored
• Ebb & Flow Line – Repairs ongoing
• Portion of Denneoord (St. Pauls, Wellington, 9th Avenue, 10th Avenue) – Repairs ongoing
• George Street, Blanco – Repairs ongoing
• Boekenhout Street, Hoekwil and Seesig line Restored
• Barnard line and Dini line, Wilderness Heights -Restored
• Saasveld – Team on site; biggest portion restored, Nelson Mandela University – Repairs ongoing

PLANNED POWER OUTAGES

All planned power outages in the following areas have been cancelled. Any current power outages are due to bad weather and infrastructure damage:
• Thembalethu

TREEs AND BRANCHES

Officials will continue cleaning up in various areas across George. There are no immediate threats at the moment.

REPORTING OF INCIDENTS

For emergencies, please use the following contact details:
• After-Hours and Emergencies: 044 801 6300
• Toll-Free Disaster Number: 087 152 9999
• Fire and Rescue: 044 801 6311 or 044 801 6300
• Law Enforcement: 044 801 6350/89

Stay safe and take necessary precautions during this period. The next update will follow at 20h30.

UPDATE 9: Inclement Weather and Emergency Incidents in George


Issued by George Municipality, 12 July 2024 @ 13:00

The George Municipality continues addressing various power outages and the cleanup of fallen trees. Currently, no roads are closed.

WEATHER WARNING

A Yellow Level 2 Warning affecting George has just been received from the South African Weather Service (SAWS). A cold front associated with a steep upper air trough is expected to result in strong to near gale westerly to north-westerly winds (40 to 60 km/h between Table Bay and Plettenberg Bay on Sunday, 14 July 2024. Wave heights of 3 to 4.56 metres are expected from Saturday, 13 July 2024 morning while the winds are only expected from the afternoon.

POWER OUTAGES

Parts of George are experiencing power outages due to bad weather. Electrical teams are dispatched to various areas:
• Berg Street Line, Hoewil – Team dispatched
• De Waal Drive – The dispatched
• Portion of Zone 4 and Zone 5 in Thembalethu – Busy with repairs to switch on soon
• Ebb & Flow Line – Contractor dispatched for removal of trees
• Portion of Denneoord (St. Pauls, Wellington, 9th Avenue, 10th Avenue) – Busy with repairs
• George Street, Blanco – Repairs ongoing
• Boekenhout Street, Hoekwil – Repairs ongoing
• Saasveld – Team on site; biggest portion restored, Nelson Mandela University still down
• Wilderness and Kleinkrantz – Eskom trip, four lines have fallen; all lines need replacement, repair work to continue this morning

PLANNED POWER OUTAGES

All planned power outages in the following areas have been cancelled. Any current power outages are due to bad weather and infrastructure damage:
• Thembalethu

TREE ACTION LIST

Officials will continue attending to fallen trees today, Friday, 12 July 2024, in the following areas:
• Wilderness Heights
• Bergsig
• Denneoord (5th Street and Meyer Streets completed)
• George CBD and surrounds (Outeniqua Weg completed)
• 7 Passes
• Darling Street, Railway line
• Glenwood

REPORTING OF INCIDENTS

For emergencies, please use the following contact details:
• After-Hours and Emergencies: 044 801 6300
• Toll-Free Disaster Number: 087 152 9999
• Fire and Rescue: 044 801 6311 or 044 801 6300
• Law Enforcement: 044 801 6350/89

Stay safe and take necessary precautions during this period.